June 6 2019 Construction Update

EXTERIOR

– EIFS (stucco) work continuing through the week of 6/10. Weather permitting, expect completion by 6/19.

– Fehn currently on site. Pond work completed. (Kinghorn to seed pond; MQP responsible for surrounding area)

– Fehn currently working in cul de sac; complete grading by 6/14.  Will continue site grading through 6/21.

– Additional fill was needed for the cul-de-sac area.  Found another septic tank!!

– Concrete curbs scheduled for 6/28-7/1.

– Backfill curbs (Fehn) 7/2-3.

– Link footings 6/24, poured walls 6/25.

– Link framing to begin week of 6/24.

– Concrete sidewalks 7/8-12.

 

INTERIOR

– Drywall and taping to continue through 6/21.

– Interior painting beginning 6/6 (prime bathrooms). Currently offices are primed, and will be working in additional areas in building. Will continue through 6/28.

– Tile work in bathrooms ready to begin week of 6/10, pending material delivery. Per Marlon, material delivery 6/13.

– Electrical rough-ins to continue through 6/21.

– Ceiling grid install to begin week of 6/24.

– Plumbing fixtures to be installed after tile is complete, and ceiling grid installed.

– Elevator work will be completed w/o 6/24

.

MQP NEEDS LIST:  Be sure to check out the NEEDS LIST!  Both Time, Talent and Treasure are needed to complete our project!

For more details from the minutes last week, click here:

Mary Queen of Peace, Pray for US!

 

footer-logo